Hello,
I had qualified WPS/PQR as per ASME IX material A 333 Gr6 welding process GTAW + SMAW with 1 time PWHT , in case of product weld have to cut that joint and re-weld and re-PWHT , my question is do we need to qualify new WPS/PQR with 2nd time PWHT or not?
Thank you and Base regards,