Hello,
To facilitate the installation of the heads inside the basin, I would like to weld (qualified weld) a temporary lug (same material) on the head to put a tension to help me position it. Then, I remove it, grind it and pass a PT (NDT). However, I do not find any indication that it is permissible or prohibited in the ASME Sect IX.
Do you have any information as to whether it is permissible to have a temporary weld on a pressure vessel ?
Thanks