Kindly assist me,
Please what convincing measures?, should i give to Client for acceptance so that spool can be erected on site?, the Spool is completely fabricated.
Details;
the fabricated spool of 28 inch Dia. with two Branch 90 degree SOB Joint of 700mm interval distance apart, with 28" x 14" Reinforcement Pad L=700mm, Thick 7.92mm STD TB,
After fabrication the reinforcement pad intersect (i.e touching each other, instead of least Gap of 50mm from both pad)
Note: the reinforcement pad already welded on the Run Pipe.
pipe ASTM A358 28" x 7.92mm thick
Reinforcement Pad STD TB, PIP 5012 28" x 14" by 7.92mm thick
Tempearture 120 Degree centrigrade
Pressure Bar 9
Test Pressure 13.49
Welding Class 3
Regards
Oliver
Planning Engineer
Port Harcourt.