Up Topic Welding Industry / Technical Discussions / POST WELD REQUIREMENT ON REPAIR WELD
- - By ravi Date 07-18-2018 12:09
CLARIFICATION  REQUIRED ON FOLLOWING QUERRY
LINEAR INDICATION OBSERVD ON AXILA FAN BALDE WELD AREA UP TO 20MM LENGTH.WE MADE 5MM DEEP GROVE IN  THIS DEFECT AREA RE WELDED.
MY QUERRY IS ,FAN IS ALREADY STRESS RELIEVED WHETHER AGIN WE HAVE TO SEND IT FOR STRESS RELIEVING OR ACCEPTED AS IT IS.
WHICH STANDARD OR CODE WE HAVE TO REFER FOR THIS TECHNICLA JUSTIFICATION
Parent - By 803056 (*****) Date 07-18-2018 14:52
The customer should be providing direction as to which fabrication standard applies if this is not an "off-the-shelf" item, i.e. custom design/build.

The fabrication standard or project specifications should address the need for stress relief or other postweld heat treatment.

Generally, if a component is postweld heat treated and a subsequent repair is performed, an additional PWHT is needed.

Al
Up Topic Welding Industry / Technical Discussions / POST WELD REQUIREMENT ON REPAIR WELD