DG,
I agree with you on this and it seems interpretation can easily be misunderstood. One reason for recommending this to ML was for the Qualification aspects ie: NDT/bend tests etc. In the fabrication industry we normally exclude gage materials or materials less than 3/16 from the bid process, and still end up doing it. If I was pursuing this matter in actual practice, I would RFI the EOR for acceptance of D1.3, if the EOR felt the WPS/PQR per D1.3 was sufficient for the application it would save a lot of time and money versus the D1.1 Section (4) qualification requirements.
I appreciate your comments, they are very educational. And I do wish it would quit raining so I could get back to work.
Thanks,
Robert