By qa
Date 01-19-2004 15:56
We have a PQR writen in accordance with ASME Section IX. and our welders are qualified to that procedure.
My question is:
Do we need to have a new PQR and WPS to weld in accordance with AWS D17.1 and meet the requirements of AWS B2.1?