Date 08-01-2000 22:17
Not quite correct: See figures 4.3, 4.4, and 4.5 - AWS D1.1-2000 (pages 105,106, 107) or for ASME Section IX, 1998 Edition, 1999 Addenda, see QW-461.3, QW-461.4, QW-461.5, and QW-461.6 (pages 140 and 141). Suprisingly they manage to agree on something. Note that the "G" designations are intended for qualification test set ups or positions and not for production - this is the clear intent of both codes if you read them carefully.
for plate: 1G is the flat test position
2G is the horizontal test position
3G is the vertical test position
4G is the overhead test position
for pipe: 1G-R - is with the pipe axis horizontal, the electrode on top
and fixed in position while the pipe is rotated underneath
2G - is with the pipe axis vertical, the joint horizontal
5G - is with the pipe axis horizontal, joint vertical (weldor
typically starts out "overhead" on bottom, goes vertical up
on sides and then flat on top (although I've known some to
start at the top, go vert down to the overhead)
6G - is with the pipe axis at 45 degrees to the horizontal
for fillet welds in plate:
1F - both plates tipped 45 degrees to the horizontal,
weld laid in flat
2F - one plate horizontal, one vertical, electrode tipped
about 45 degrees, laid in on top of horizontal plate. This is
what a lot of weldors call flat
3F - both plates vertical, typical vertical up (or down)
position
4F - one plate horizontal, one plate vertical (but hanging
down from the horizontal one) weld is made "overhead"
I'm getting lazy so look at the references above for the pipe fillet weld test positions.