- - By shadowplay Date 02-18-2008 12:56
Dear sirs
Can you explain me if Preheat - Interpass- and Preheat maintenance are mandatory for
F22to F22 seal welds
or F22 + Stellite Overlay?
If Yes what temperature are ?

Many thanks
Parent - - By shadowplay Date 02-19-2008 09:06
anyone can help me ?
Parent - - By Stephan (***) Date 02-19-2008 09:44
shadowplay,

I'm sure others will point you in the right direction much better than me, but for the first please have a look into the attached pdf.

Best regards,
Stephan
Attachment: Kobelco.pdf (295k)
Parent - - By shadowplay Date 02-19-2008 10:36
Many thanks Stephan
Parent - By jon20013 (*****) Date 02-19-2008 11:44
Good stuff from Stephan, as usual!  If you were working in my shop / site, I would make a brash statement that yes, preheat is mandatory and maybe even especially where Stellite hardfacing is applied.  However, most things in our business have too many variables to make such brash statements.  You mention seal welds but don't tell us the applications or thickness of materials you're working with... are these seal welds for threaded connections?  Codes often dictate mandatory preheat, interpass and PWHT.  It's a bit too difficult to make a sound call in your instance without sounding brash, as I mentioned earlier.