Not logged inAmerican Welding Society Forum
Forum AWS Website Help Search Login
Up Topic Welding Industry / Technical Discussions / Tack vs Continual tack vs Backing vs Seal Pass vs Root Pass?
- - By Bowler_Hat (**) Date 10-09-2015 13:46
Hey All- Ready for a long question? (Research included!)

As with any new position, the difference of terms here tend to be quite bother some. So a nit-picky question that I look to you, the educated and experienced, to help me sort out.

The Plant Manager here tends to flare up any time he hears the word 'backing'. Specifically, we deal with SAW. Two beveled plates are brought together to make a double V groove, 'tacked' into place, and then a SAW pass is ran on both sides, consuming/remelting the 'tacks' entirely, producing CJP.

The issue is, on the shop floor this tack is often called 'backing'. However, the P.M. first called this a 'continual tack', and now in his last polite discussion called it a seal pass.

With as much confusion as I've seen around here, I fear they may have investigated this topic when the company first started and have been cherry-picking what works best for them ever since.

What I know comes from D1.1:

5.18.1 General Requirements
(1) Tack welds and construction aid welds shall be made with a qualified or prequalified WPS and by qualified personnel.

(2) Tack welds that are not incorporated in the final welds, and construction aid welds that are not removed, shall meet visual inspection requirements before a member is accepted.

5.18.2 Exclusion Tack welds and constriction aid welds are permitted except that:

(1) in tension zones of cyclically loaded structures, there shall  be no tack welds not incorporated into the final weld except as permitted by 2.16.2, nor construction aid welds. Location more than 1/6 of depth of the web from tension flanges of beams or grinders are considered outside the tension zone.

(2) On members made of quenched and tempered steel with specified yield strength grater than 70ksi [485 MPa], tack welds outside the final weld and construction aid welds shall require the approval of the Engineer.

5.18.3 Removal At locations other than in 5.18.2, tack welds and construction aid welds, not incorporated into the final welds, shall be removed when required by the Engineer.

5.18.4 Additional Tack Weld Requirements
(1) Tack welds incorporated into final welds shall be made with electrodes meeting the requirements of the final welds. These welds shall be cleaned prior to incorporation.

(2) Multipass tack welds shall have cascaded ends or be otherwise prepared for incorporation into the final weld.

(3) Tack welds incorporated into the final welds that are qualified with notch toughness or are required to be made with filler metal classified with notch toughness shall be made with compatible filler metals.

5.18.5 Additional Requirements for Tack Welds incorporated into SAW Welds. The following shall apply in addition to 5.18.4 requirements.

(1) Preheat is not required for single pass tack welds remelted by continuous SAW welds. This is an exception to the qualification requirements of 5.18.1

(2) Fillet tack welds shall not exceed 3/8 in [10 mm]  and shall not produce objectionable changes in the appearance of the weld surface.

(3) tack welds in the roots of joints requiring specific root penetration shall not result in decreased penetration.

(4) tack welds not conforming to the requirements of (2) and (3) shall be removed or reduced in size by any suitable means before welding.

(5) Tack welds in the root of a joint with steel backing less than 5/16 [8 mm] thick shall be removed or made continuous for the full length of the joint using SMAW with low-hydrogen electrodes, GMAW, or FCAW-G

Walking my way through all of that...

-From my perspective, we match 5.18.1 (1), part (2) doesn't apply to us here.

-Our finished product here isn't made of quenched or tempered steel, though while our product is cyclically loaded, I don't know of any tension zone, so I believe 5.18.2 doesn't apply here.

-Our tacks are consumed or remelted in the SAW passes, so 5.18.3 doesn't apply here.

-Our tacks are made with electrodes meeting the requirements of the final weld, and we clean them before welding on them...so we meet 5.18.4 (1).

-The tacks aren't multi pass, so 5.18.4(2)  doesn't apply.

-All of our PQR's go through a CVN, and our GMAW is commpatable with our SAW.

-This is a single pass tack weld that is remelted by the following SAW pass, so no preheat is required.

-We're welding a CJP double V groove joint, so 5.18.5 doesn't apply.

-Our tacks are in the root and CJP is required,  our tacks haven't decrease the penetration (all welds are inspected with UT). So we're good here.

-Our tacks meet (2) and (3), so (4) doesn't apply.

-We don't have steel backing, so (5) doesn't apply here.

In AWS A3.0M/A3.0:2010 backing is defined as:

A material or device placed against the back side of the joint adjacent to the joint root, or at both sides of a joint in electroslag and electrogas welding, to support and shield molten weld metal. The material may be partially fused or remain unfused during welding and may be either metal or nonmetal. See Figures B.8(D), B.12, and B.37.

tack weld is defined as:

A weld made to hold the parts of a weldment in proper alignment until the final welds are made.

root pass is defined as:

A weld pass made to produce a root bead.

and because that definition included another term...

root bead is defined as

A weld bead extending into or including part or all of the joint root.

Figure B.8(D) is a single V-groove, Figure B.12 is Split Pipe Backing, and B.37 depicts Electroslag Welding.

I haven't found anything about a 'continual tack' or a 'seal pass', are these older terms, or just made up terms?

Looking at all of this I'm inclined to say that our GMAW pass is a 'single pass tack weld'. Specifically, from my perspective, the tack that we put in doesn't penetrate the root, it leaves a tiny gap, that when viewed from the edge, one can see. Though with that said, I'm sure that root has had fusion made by this tack.

So...what are your thoughts on this topic?

Thank you for reading this far though, this community has been most helpful!

I'll conclude by saying that I am a novice CWI and am worried to being 'led astray'.

Ex. Trying to convince my employer that, 'Hey, the WPS that we operate under specify checking the preheat and interpass temperature with a contact polymer only...and we don't have any in house.' was a struggle. Only after some documentation and explanation  (Instead of wanting to purchase the tempilstiks, the P.M. blamed improperly written WPSs...and found they were written and signed off by him...it wouldn't be bad if he wasn't also a CWI).
Parent - - By TimGary (****) Date 10-09-2015 15:05
Hello Bowler_Hat,

First, let me compliment you on posting such a thorough and previously researched question.

Second, I need to state that I don't have my D1.1 with me at the moment, so my reply is opinion based only, so don't take it to the bank until you get the several replies I assume this will generate.

Assuming that by continuous tack and seal pass, you mean that this GMAW "tack weld" is continuous from one end of the joint to the other.
Also assuming that the reason for this is to prevent the first SAW pass from blowing through the joint root.

Opinions -
1. This is not a tack, it is a root pass.
2. This is not a backing weld as it is inside a double V groove.
3. The reason it's being called anything other than a root pass is a loose interpretation of this comment copied from your post:

   "5.18.5 Additional Requirements for Tack Welds incorporated into SAW Welds. The following shall apply in addition to 5.18.4 requirements.
(1) Preheat is not required for single pass tack welds remelted by continuous SAW welds. This is an exception to the qualification requirements of 5.18.1"

which is a means of not having to go through the expense of preheating for a root pass, as required.
4. The reason joints receiving a root pass need to be preheated, when material conditions require, is to help prevent it from cracking, which if said crack is welded over, may remain in the joint and cause failure.
5. That these welds are UT'd is good, and provides a little bit of warm fuzzy feeling, but is every such joint UT'd? Also we need to keep in mind that UT is not infallible.
6. This is a typical method of a contractor or manufacturer to reduce costs by cutting corners on quality because if or when this practice causes a failure, it will be long after the project is done and has been paid for.

Some what cynically,
Tim
Parent - - By SCOTTN (***) Date 10-09-2015 18:44
Bowler Hat,

I’ve never heard of “continual tack” or “seal pass” and to the best of my knowledge neither one is recognized by A3.0, and therefore non-standard terms.  If it’s continuous and it’s intended to serve as backing, then it’s a “backing weld”, which is defined in A3.0 as backing, in the form of a weld.

You indicated that “two beveled plates are brought together to make a double V groove, 'tacked' into place, and then a SAW pass is ran on both sides, consuming/remelting the 'tacks' entirely, producing CJP.

Prequalified joint designations for a CJP double bevel groove for the SAW process are either going to be a B-U3a-S, or a B-U3c-S, which both require backgouging. 

If you’re using this “continual tack” as backing and as you say, “consuming/remelting the 'tacks' entirely, producing CJP”, then D1.1 does not recognize this as being a prequalified joint because the backgouging has been eliminated.  Furthermore, there is no prequalified double V groove joint with backing.  So, unless the WPS was generated from a qualified PQR, showing a “backing weld” and as you put it… "subsequent consuming/remelting the 'tacks' and entirely, producing CJP", then the WPS is not valid.
Parent - By In Tension (**) Date 10-09-2015 23:16
Bowler Hat,
Question well put.  I also don't have D1.1 with me so I'm shooting from the hip.
I've actually had a similar situation in which "single pass tack" was misinterpreted (due to the word "pass") as opposed to the term being contrasted with, and related to, "multiple pass tack."  But, in that scenario it was just a single weld from a well-intentioned welder and it was an easy fix.  In your case the terminology is integrated into your welding program and needs to addressed.
With this being an initial full-length pass in a groove weld and incorporated into the final weld it would take a strong argument to convince me that it's anything other than a root pass.  But, other than a terminology disagreement what's at stake?  Is this "continuous tack" term being used in conjunction with 5.18.5 to justify not preheating the joint prior to 'tacking,' as TimGary suggests?  If that's the case, and if your WPS doesn't reflect the situation, then your procedure needs to be brought into alignment with your welding conditions, or vice versa.  If the procedure is properly qualified then the only ramification is having to deal with an obstinate plant manager.  I don't think you'll find any code violations in their method as long as the procedure is valid.  It's simply a root pass and not a tack weld.  Make sure your WPS clarifies it as such.
Do they use actual tack welds to secure the plates prior to the "continuous tack"?  That would be annoying.
Terminology isn't always as straight-forward as it seems on the surface.  Language in general is fascinating.  Sometimes during disputes with production fellas I can't help but wonder if we're both reading the same thing even though I know we are.  And sometimes people are just being willfully ignorant to exert an agenda.
As an example, and thought exercise, I could make a pretty good argument that a GMAW pass that bridged the root of a double-V and didn't fuse any root could be considered a backing weld in function and intent.  But does it cease to be a backing weld when it's subsequently filled and capped?  Could I be right and wrong at the same time?  Things like this keep it interesting.
- - By welderbrent (*****) Date 10-09-2015 22:56
While the correct designation is 'seal weld' it is most definitely in A3.0 Terms and Defs. 

It is often referenced in the tail of the welding symbol as either of the above to indicate a weld pass intended to seal any leakage generally in applications with some form of liquid involved.

But, I have seen it used to form the 'root' for SAW and other welding procedures.

Now, it is in no way a 'tack' weld.  Not by the application.  While I know D1.1 says a tack weld shall be made continuous for certain applications, a TACK weld is not a weld that is continuous in a joint.  This is misleading as once you add any dimension to it beyond the strength required to hold everything in place to continue with the welding procedure it is no longer a TACK weld.  When used thus it is either a seal weld or most properly a weld pass in the root.

For instance, if it is a 'tack' weld then a person qualified as a 'tack' welder could weld it right?  So, why not just qualify all my welders as tack welders using the 2" long test and then claim they were only tack welding even though they were utilizing multi-pass tacks and full length tacks?  :eek: 

There does need to be some clarification on this in my opinion and I will check through previous official interpretations but I don't remember seeing anything in this area. 

It could actually be considered a 'backing' weld as it is performing in many ways the definition of such, a weld used for backing.  That would be more accurate than a seal weld as it is not really sealing anything unless the root is so wide that it is keeping the flux from falling through prior to the welding operation. 

Just my two tin pennies worth.

He Is In Control, Have a Great Day,  Brent
Parent - - By In Tension (**) Date 10-09-2015 23:25 Edited 10-09-2015 23:27
I agree, Brent, it's all about purpose.  And for the original poster's situation the purpose of the pass is clearly meant for backing and not for securing the pieces (tacking).  I'm curious as to why the Plant Manager insists on it being called a continuous tack.  He's obviously intent on calling it that and I wonder what corners he's trying to be cut by doing so.
Parent - - By 803056 (*****) Date 10-10-2015 00:46 Edited 10-10-2015 01:37
Saw something in regards to this question written by D. Miller. I'll see if I can find it. It may have been an interpretation of D1.1 regarding tack welds.

Well I didn't find what I was looking for in the few minutes I looked, so I'll attempt to paraphrase what was stated in the write-up to the best of my limited recollection. The question was in regards to the acceptability of using a continuous tack weld, running the full length of a joint, to hold the parts in alignment and to contain the flux while performing submerged arc welding. The premise was that the tack weld was completely remelted, consumed, and incorporated into the first bead deposited by SAW.

The response was that there is no length limitation imposed on a tack weld, thus it can extend from one end of the joint to the other and as long as it hold the parts in alignment, all is fine with the world. As long as the tack weld is remelted and consumed by the next bead deposited by SAW, the relevant provisions of D1.1 are applicable.  

With that in mind, I see nothing wrong is calling the weld a continuous tack weld.

Al
Parent - - By Lawrence (*****) Date 10-10-2015 02:11
Parent - - By welderbrent (*****) Date 10-10-2015 03:09
Great, thanks Lawrence.  Great article by Mr Miller.

BUT, I still have a hard time justifying the use of 'tack' weld for a continuous weld several feet long.  In my mind it is no longer meeting the definition nor the practical application of a tack weld.  It is either a backing or seal weld and/or a root weld bead.  But to say it is still a tack weld.  Grasping at straws to my pea brain.

But, I'm no D. Miller, Lawrence, nor Al Moore.  I yield though reluctantly.

He Is In Control, Have a Great Day,  Brent
Parent - - By Lawrence (*****) Date 10-10-2015 14:57
I have no dog in this fight...

Just posted Dr. Millers article because Al mentioned it.   Although Duane does appear to speak pretty closely to the issue at hand.

Not sure if I reviewed all the OP's excellent statements well enough.... 

But if the PQR was run in the manner that production is being run........ Who cares about nomenclature beyond a water cooler debate....?   If the process has been proven I don't see a problem.
Parent - By 803056 (*****) Date 10-10-2015 21:37
Amen.

Al
Parent - - By welderbrent (*****) Date 10-11-2015 00:05
Agreed...but, it isn't a fight.  (I know, just a phrase)

Brent
Parent - By kcd616 (***) Date 10-11-2015 01:04
this is just imho
but a tack is what a fitter does when tacking the pieces together
a weld anything else the print calls out after fitting
just my thoughts
sincerely
Kent
Parent - By SCOTTN (***) Date 10-11-2015 10:35
A fight? Ain't nobody gonna mess with me.  A lot of people don't know this about me, but I can kill a man with my bare feet. My only problem is that I keep getting beat up before I can get my shoes off.
Parent - By Bowler_Hat (**) Date 10-12-2015 14:43
All of our welds here have corresponding PQR's, no pre qualified. :sad:
Parent - By Bowler_Hat (**) Date 10-12-2015 14:24
I have that printed and hanging in my wall...forgot to mention that in the original post. Sadly, the sections of the code quoted in this article, no longer reflect the current. Specifically, 5.18.2 (2) is quoted as, "Removal of discontinuities, such as undercut, unfilled craters, and porosity before the final SAW is not required." Where in D1.1 2010 5.18.2 is a different section all together Exclusions.

While there are many good details still in this article, I fear it's a bit outdated.
Parent - By Bowler_Hat (**) Date 10-12-2015 14:27
It should be noted, if this pass were not there, this piece would not be able to be welded using the SAW process. Specifically these large steel sheets tend to have a lot of 'spring in them' 10ton plates...fun stuff. The station that actually puts in this tack/backing, the operator is called 'roll/fit up'. Though, I'm still curious as you, why the P.M. does as they do. Thanks!
Parent - - By Bowler_Hat (**) Date 10-12-2015 14:29 Edited 10-12-2015 18:18
Hey Brent,

Could you please point to which page of A3.0 Terms and Defs 'Seal Pass' is on, I've searched through it and can not, for the life of me locate it.

Cheers!
Parent - - By welderbrent (*****) Date 10-12-2015 14:45
Page 33 of the 2001 edition on my computer.  Will have to find a newer edition to confirm it is still there.  Most of my books are in storage as we are remodeling the home we are moving into.  Have been living in our RV for the past 6 mo.

Brent
Parent - - By Bowler_Hat (**) Date 10-12-2015 18:18
No harm done. I did find 'Seal Weld" in A3.0M/A3.0:2010 page 36(I believe this is the most current). Just a matter of that one different, weld and pass. So huzzah! We found it.
Parent - By In Tension (**) Date 10-12-2015 23:34
Yeah, a seal weld is most definitely a thing though it's usually used in a different context, a weld intended primarily to provide a specific degree of tightness against leakage, and is often used as precluding it from being a strength weld. 
I've read that article before but guess I didn't consider the implications.  Of course, it makes total sense.  But I also think it's possible for "D. Miller, PE, PhD" to be at odds with "AWS D1.1 Chairman D. Miller" at times, depending on his angle when he's speaking/writing.  If the full-length tack weld is to be a legit thing then it should be defined/clarified somewhere in the code.... if only for Brent's example of how the welder making such a tack weld is required to be qualified.  No doubt we'd all put our boot down (or take it off, in Scott's case) when a tack welder is making such tacks.  Where is the line drawn?  I don't like the grayish "you'll know it when you see it" aspect. 
To be clear, I don't see anything wrong with the way Bowler Hat's guys are doing things (it's pretty common practice) but I might be rolling my eyes a little bit until I got used to it.  There are bigger fish to fry.
Parent - By Cumminsguy71 (*****) Date 10-18-2015 11:41
I've seen/heard the term "Seal weld" on a few structural jobs called out by the engineers. We overlay steel on existing steel and they have called out "seal welding" the vertical seams in between the structural welds merely to keep out moisture. The engineer when asked if we could use 6010 downhill (faster) said it had no structural relevance and wanted minimal penetration, just wanted to seal out the elements.
- By kcd616 (***) Date 10-13-2015 11:40
from victor aka esab
doc I just posted
Tack Weld: A weld made to hold the parts of a weldment in proper alignment until the final welds are made.
sincerely,
Kent
Up Topic Welding Industry / Technical Discussions / Tack vs Continual tack vs Backing vs Seal Pass vs Root Pass?

Powered by mwForum 2.29.2 © 1999-2013 Markus Wichitill