I agree,
The backing bars may create false indications which may be constued as LOF, etc.. FEMA and newer procedures require the removal of the backing ; and some engineers require and additional reinforceing fillet weld at the point of stress.
It seems the botton flange of the beam receives the most stress during a sesmic event.